Streets:
-
Staff installed
10 Daughters of Charity 200 Year Celebration Banners
-
Staff has
repaired a number of street lights
-
Staff salt
treated a number of streets
-
Staff made
a number of cold patch street repairs
Water:
-
Rainbow Lake
is now full and holding at the spillway level
-
The roughing
filters are now being backwashed twice per day
and the DE filters are being done once per week
-
Staff is continuing to perform a
system loss survey. As part thereof we have
replaced a valve on Riffle Road and repaired a leak on
Creamery Way
-
-
Staff has been working with McCrone
Engineering and Contractors related to additional
testing of wells & and "J" pursuant to
the design of the Emit Gardens Water Plant
-
Water
production and consumption. We produced and
purchased an average of 335,621 gpd. We consumed
an average of 283,385 gpd
-
The
difference is "Backwash Water" ...(15.5%). We purchased
318,950 gals.
of water from MSM this month.
-
47.1% of this
water came from wells
-
3.4% of this water
came from Mt. St. Mary's
-
49.5% of this
water came from Rainbow Lake
Wastewater:
-
The overland
and flow treatment system remains shut-down for the
seaseon
-
Staff had
roto-rooter cut roots out of the sewer main on Park
Drive in Emmit Gardens
-
We received
about 0.8 inches of precipitation this month (the
average is 3.0 inches)
-
Wastewater
Treatment:
-
We treated
an average of 365,000 gpd (consumed 283,385 gpd)
which means that 22.4% of the wastewater treated this
month was "wild water".
-
We
experienced no spills of untreated sewerage
during the month of February
-
We did not
exceed the plant's design capacity in the month of
February
Trash:
Parks:
-
Staff made all
standard checks and emptied trash cans
-
Staff made a few repairs to the fencing
and the back-stops at the Little League Fields
-
Staff
worked on the new ceiling in the pool pavilion
Meetings
Attended:
-
02/02
Frederick County District Court to present the Town's
case related to a parking ticket
-
02/10 Staff
water capacity plan meeting
-
02/10 Building
lockdown meeting
-
02/12 NCTRAC
Transportation Planning meeting
-
02/16 Pool
Contractor meeting
-
02/16
Mayor's staff meeting
-
02/17
Scenic ByWays meeting
-
02/18
Meeting with Emit Gardens Water Plant design engineers
-
02/19
Frederick Co. Commissioners and the municipalities
monthly meeting - stimulus funding
-
02/23
Meeting with Sue and Frederick County Planning staff
related to municipal growth boundary
-
02/24
Staff Clerk's meeting
-
02/25
Staff water capacity plan meeting
-
02/26
Frederick County MML meeting discussed WTE and
Stimulus Funding
list